# The National Grid (North London Reinforcement Project) Order 2014, Paragraph 13: Construction environmental management plan

Extent: E+W+S

(1) No stage of the authorised development shall commence until a construction environmental management plan for that stage specifying measures to be used to minimise the impacts of construction works, such as means of minimising pollution from dust, noise, vibration and lighting, wheel cleansing facilities, routes for construction traffic and working hours and reflecting the measures included in the environmental measures document has, after consultation with the Lee Valley Regional Park Authority where it refers to any land within the boundary of the Lee Valley Regional Park, been approved by the relevant planning authority.
(2) All construction works shall be undertaken in accordance with the construction environmental management plan prepared in accordance with requirement 13(1), unless otherwise agreed by the relevant planning authority.

---
Source: https://www.legislation.gov.uk/uksi/2014/1052/schedule/2/paragraph/13 (the official version)
Page: https://openlegislation.uk/national-grid-north-london-reinforcement-project-order-2014/schedule-2/paragraph-13
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.