# The National Grid (North London Reinforcement Project) Order 2014, Paragraph 2: Time Limits

Extent: E+W+S

The authorised development must be commenced within 5 years of the date of this Order.

---
Source: https://www.legislation.gov.uk/uksi/2014/1052/schedule/2/paragraph/2 (the official version)
Page: https://openlegislation.uk/national-grid-north-london-reinforcement-project-order-2014/schedule-2/paragraph-2
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.