# The National Grid (North London Reinforcement Project) Order 2014, Paragraph 5: Landscaping

Extent: E+W+S

(1) No stage of the authorised development shall commence until a written landscaping scheme for that stage has, after consultation with the Lee Valley Regional Park Authority where the scheme refers to any land within the boundary of the Lee Valley Regional Park, been submitted to and approved by the relevant planning authority.
(2) Each landscaping scheme submitted under requirement 5(1) shall reflect the environmental measures set out in the environmental measures document.
(3) Where submitted for land in the designated Enfield Lock Conservation Area, a landscaping scheme submitted under requirement 5(1) shall include measures that preserve the character and appearance of the Enfield Lock Conservation Area, to the satisfaction of the relevant planning authority.
(4) Each landscaping scheme submitted under requirement 5(1) shall include details of—
(a) retained landscape features;
(b) location, number, species, size and planting density of any proposed planting;
(c) cultivation, importing of materials and other operations to ensure plant establishment;
(d) implementation timetables for all landscaping;
(e) temporary fencing that complies with current best practice to protect trees and hedgerows adjacent to the works;
(f) the dimensions and materials for new sections of pedestrian or cycle paths where applicable; and
(g) the colour of permanent security fencing around infrastructure.

---
Source: https://www.legislation.gov.uk/uksi/2014/1052/schedule/2/paragraph/5 (the official version)
Page: https://openlegislation.uk/national-grid-north-london-reinforcement-project-order-2014/schedule-2/paragraph-5
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.