# The National Grid (Richborough Connection Project) (Correction) Order 2018, Article 2: Corrections


Corrections to be made to the National Grid (Richborough Connection Project) Development Consent Order 2017 are set out in the table in the Schedule to this Order, where—
(a) column 1 sets out where the correction is to be made;
(b) column 2 sets out how the correction is to be made; and
(c) column 3 sets out the text to be substituted, inserted or omitted.

---
Source: https://www.legislation.gov.uk/uksi/2018/572/article/2 (the official version)
Page: https://openlegislation.uk/national-grid-richborough-connection-project-correction-order-2018/article-2
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.