{
  "url": "https://openlegislation.uk/national-grid-richborough-connection-project-development-consent-order-2017/article-14",
  "json_url": "https://openlegislation.uk/national-grid-richborough-connection-project-development-consent-order-2017/article-14.json",
  "legislation": "uksi/2017/817",
  "legislation_title": "The National Grid (Richborough Connection Project) Development Consent Order 2017",
  "legislation_url": "https://openlegislation.uk/national-grid-richborough-connection-project-development-consent-order-2017",
  "path": "article/14",
  "kind": "article",
  "number": "14",
  "heading": "Access to works",
  "text": "(1) The undertaker may, for the purposes of the authorised development and with the consent of the relevant planning authority, after consultation with the highway authority, form and lay out such other means of access or improve existing means of access, at such locations within the Order limits as the undertaker reasonably requires for the purposes of the authorised development.\n(2) If a relevant planning authority which receives an application for consent under paragraph (1) fails to notify the undertaker of its decision before the end of the period of 28 days beginning with the date on which the application was made, it is deemed to have granted consent.",
  "extent": "E+W",
  "status": null,
  "version": "current",
  "annotations": [
    {
      "type": "I",
      "label": "I1",
      "text": "Art. 14 in force at 24.8.2017, see art. 1"
    }
  ],
  "outstanding_effects": [],
  "provenance": {
    "source": "legislation.gov.uk",
    "source_url": "https://www.legislation.gov.uk/uksi/2017/817/article/14",
    "retrieved_at": "2026-10-28T23:08:57.690280+00:00"
  },
  "licence": "Open Government Licence v3.0",
  "licence_url": "https://www.nationalarchives.gov.uk/doc/open-government-licence/version/3/",
  "attribution": "Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives."
}