# The National Grid (Richborough Connection Project) Development Consent Order 2017, Article 34: Deemed marine licence

Extent: E+W

The undertaker is deemed to have been granted the licence contained in Schedule 9 (deemed marine licence) to this Order, to carry out the works and make the deposits described in that licence and subject to the licence conditions which are deemed to have been attached to the licence by the Secretary of State under Part 4 of the 2009 Act.

---
Source: https://www.legislation.gov.uk/uksi/2017/817/article/34 (the official version)