Works to construct a temporary site compound, at the location shown on Works Plan Sheet 17 to include—
(a) temporary car parking, hard standing and roadways;
(b) temporary offices and staff welfare portable cabins;
(c) temporary materials, tools and fuel storage areas;
(d) temporary storage of plant and equipment;
(e) wheel cleaning facilities;
(f) security fencing; and
(g) construction and security lighting.

---