# The National Grid (Richborough Connection Project) Development Consent Order 2017, In the District of Thanet

Extent: E+W

Works to allow the construction and installation of two single circuit 132kV overhead electric lines supported by wooden poles and the installation of conductors, insulators and fittings between pylons PX56 and PX60. The removal of existing pylons PX57, PX58 and PX59 and associated conductors, insulators and fittings as shown on Works Plan Sheets 12 and 13.

---
Source: https://www.legislation.gov.uk/uksi/2017/817/schedule/1/chapter/2/crossheading/in-the-district-of-thanetn1 (the official version)
Page: https://openlegislation.uk/national-grid-richborough-connection-project-development-consent-order-2017/schedule-1/chapter-2/crossheading-in-the-district-of-thanetn1
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.