# The National Grid (Richborough Connection Project) Development Consent Order 2017, Paragraph 4

Extent: E+W

Regardless of any provision in this Order or anything shown on the land plans, the undertaker may not acquire any apparatus otherwise than by agreement with the relevant statutory undertaker.

---
Source: https://www.legislation.gov.uk/uksi/2017/817/schedule/14/part/1/paragraph/4 (the official version)
Page: https://openlegislation.uk/national-grid-richborough-connection-project-development-consent-order-2017/schedule-14/part-1/paragraph-4
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.