# The National Grid (Richborough Connection Project) Development Consent Order 2017, Paragraph 2

Extent: E+W

(1) Before commencing the construction of, or the carrying out of any work which involves interference with a highway, the undertaker shall submit to the highway authority for its approval plans, drawings and particulars (in this paragraph referred to as “relevant plans”) relating to the interference, and the works shall not be carried out except in accordance with the relevant plans submitted to, and approved by, the highway authority.
(2) If within 28 days after the relevant plans have been submitted the highway authority has not approved or disapproved them, it shall be deemed to have approved the relevant plans as submitted.

---
Source: https://www.legislation.gov.uk/uksi/2017/817/schedule/14/part/3/paragraph/2 (the official version)
Page: https://openlegislation.uk/national-grid-richborough-connection-project-development-consent-order-2017/schedule-14/part-3/paragraph-2
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.