# The National Grid (Richborough Connection Project) Development Consent Order 2017, Paragraph 8

Extent: E+W

The undertaker shall not, except with the consent of the highway authority, erect or retain on or over a highway to which the public continues to have access any scaffolding or other structure which obstructs the highway.

---
Source: https://www.legislation.gov.uk/uksi/2017/817/schedule/14/part/3/paragraph/8 (the official version)
Page: https://openlegislation.uk/national-grid-richborough-connection-project-development-consent-order-2017/schedule-14/part-3/paragraph-8
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.