# The National Grid (Richborough Connection Project) Development Consent Order 2017, Paragraph 14


Notwithstanding any provision in this Order including the limits of deviation, no part of the authorised development comprising a conductor may be constructed or installed on or over any part of SEW’s land at a level which is more than 50 centimetres lower than the level of that conductor as shown on the design drawings.

---