# The National Grid (Richborough Connection Project) Development Consent Order 2017, Paragraph 16


The undertaker at its own cost must within 18 months (unless otherwise agreed with SEW) of planning permission or other statutory consent being granted for the Broad Oak Reservoir, fit and thereafter maintain bird flight diverters to the overhead lines between Pylons PC7 to PC10, provided that a condition or requirement of any permission or consent or obligation under any relevant instrument within or connected to the planning permission or other statutory consent for the Broad Oak Reservoir confirms that the fitting of bird flight diverters is required.

---
Source: https://www.legislation.gov.uk/uksi/2017/817/schedule/14/part/5/paragraph/16 (the official version)
Page: https://openlegislation.uk/national-grid-richborough-connection-project-development-consent-order-2017/schedule-14/part-5/paragraph-16
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.