# The National Grid (Richborough Connection Project) Development Consent Order 2017, Paragraph 9


The undertaker must not in the exercise of the powers conferred by this Order permanently or for any longer than 7 consecutive days prevent pedestrian or vehicular access to any apparatus or alternative apparatus, unless preventing such access is with the consent of SEW.

---