# The National Grid (Richborough Connection Project) Development Consent Order 2017, Paragraph 17: Clearance over the tidal River Stour

Extent: E+W

No part of any 400kV overhead electric line shall be installed or maintained directly above the tidal River Stour at a height of less than 10 metres above the mean high water level of that river.

---
Source: https://www.legislation.gov.uk/uksi/2017/817/schedule/3/paragraph/17 (the official version)