# The National Grid (Richborough Connection Project) Development Consent Order 2017, Paragraph 18: Removal of UK Power Networks Works

Extent: E+W

Any existing UK Power Networks infrastructure to be removed as part of the UK Power Networks works must be removed no later than 36 months after the 400kV overhead line (Work No.1 of Schedule 1 (authorised development)) is first brought into operational use.

---