# The National Grid (Richborough Connection Project) Development Consent Order 2017, Paragraph 2: Time Limits

Extent: E+W

The authorised development must be commenced within 5 years of the date of this Order.

---
Source: https://www.legislation.gov.uk/uksi/2017/817/schedule/3/paragraph/2 (the official version)
Page: https://openlegislation.uk/national-grid-richborough-connection-project-development-consent-order-2017/schedule-3/paragraph-2
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.