{
  "url": "https://openlegislation.uk/national-grid-richborough-connection-project-development-consent-order-2017/schedule-3/paragraph-4",
  "json_url": "https://openlegislation.uk/national-grid-richborough-connection-project-development-consent-order-2017/schedule-3/paragraph-4.json",
  "legislation": "uksi/2017/817",
  "legislation_title": "The National Grid (Richborough Connection Project) Development Consent Order 2017",
  "legislation_url": "https://openlegislation.uk/national-grid-richborough-connection-project-development-consent-order-2017",
  "path": "schedule/3/paragraph/4",
  "kind": "paragraph",
  "number": "4",
  "heading": "Stages of authorised development",
  "text": "(1) The authorised development may not commence until a written scheme setting out all the stages of the authorised development has been submitted to and approved by the relevant planning authority following consultation with the highway authority.\n(2) Written notice of the commencement and completion of each stage of the authorised development and the operational use of that stage of the authorised development must be given to the relevant planning authority within ten business days prior to the commencement of that stage or operational use of that stage or within 10 business days of completion of that stage.",
  "extent": "E+W",
  "status": null,
  "version": "current",
  "annotations": [
    {
      "type": "I",
      "label": "I1",
      "text": "Sch. 3 para. 4 in force at 24.8.2017, see art. 1"
    }
  ],
  "outstanding_effects": [],
  "provenance": {
    "source": "legislation.gov.uk",
    "source_url": "https://www.legislation.gov.uk/uksi/2017/817/schedule/3/paragraph/4",
    "retrieved_at": "2026-10-28T23:08:57.690280+00:00"
  },
  "licence": "Open Government Licence v3.0",
  "licence_url": "https://www.nationalarchives.gov.uk/doc/open-government-licence/version/3/",
  "attribution": "Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives."
}