# The National Grid (Richborough Connection Project) Development Consent Order 2017, Paragraph 6: Approval and implementation of construction mitigation plans

Extent: E+W

(1) No stage of the authorised development may commence until, for that stage, the following plans, scheme and strategy to minimise the impacts of construction works have been submitted to and approved by the relevant planning authority after consultation with any of the relevant sewerage authority, the relevant drainage authority, Natural England and the Environment Agency, as may be appropriate to the relevant plan, scheme or strategy concerned—
(a) Soil and Aftercare Management Plan;
(b) Drainage Management Plan;
(c) Pollution Incident Control Plan;
(d) Lighting Scheme;
(e) Emergency Response Plan for Flood Events;
(f) Site Waste Management Plan;
(g) Tree and Hedgerow Protection Strategy; and
(h) Travel Plan.
(2) The construction works for each stage of the authorised development and mitigation works to minimise the impact of construction must be carried out in accordance with the approved plans, scheme and strategy referred to in sub-paragraph (1) or with any amended plans, scheme or strategy that may subsequently be approved by the relevant planning authority.

---
Source: https://www.legislation.gov.uk/uksi/2017/817/schedule/3/paragraph/6 (the official version)
Page: https://openlegislation.uk/national-grid-richborough-connection-project-development-consent-order-2017/schedule-3/paragraph-6
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.