# The National Grid (Richborough Connection Project) Development Consent Order 2017, Paragraph 5: Interpretation of Schedule 4

Extent: E+W

(1) In this Schedule—
“the appeal parties” means the relevant authority, the requirement consultee and the undertaker;
“relevant authority” means the relevant planning authority, highway authority, street authority, Environment Agency, the Marine Management Organisation, Natural England, relevant drainage authority or relevant owner of a watercourse, sewer or drain as may be appropriate to the consent or approval sought; and
“requirement consultee” means any body named in a Requirement which is the subject of an appeal as a body to be consulted by the relevant authority in discharging that Requirement.

---
Source: https://www.legislation.gov.uk/uksi/2017/817/schedule/4/paragraph/5 (the official version)
Page: https://openlegislation.uk/national-grid-richborough-connection-project-development-consent-order-2017/schedule-4/paragraph-5
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.