The licence holder must inform the relevant harbour authorities in writing of the licensed activities (including timetable, contractor and vessel details) at least 20 business days prior to commencement of any licensed activity. The contact details are as follows—
Sandwich Port and Haven Commissioners, 1 Potter Street, Sandwich, Kent CT13 9DR, Tel: 01304 612162;
Thanet District Council, The Harbour Offices, Military Road, Ramsgate, CT11 LQ, Email: portoframsgate@thanet.gov.uk , Tel: 01843 687661.

---