# The National Grid (Richborough Connection Project) Development Consent Order 2017, Paragraph 13


Bunding and/or storage facilities must be installed to contain and prevent the release of fuel oils, lubricating fluids and chemicals associated with vessels, plant and equipment into the marine environment.

---
Source: https://www.legislation.gov.uk/uksi/2017/817/schedule/9/paragraph/13 (the official version)
Page: https://openlegislation.uk/national-grid-richborough-connection-project-development-consent-order-2017/schedule-9/paragraph-13
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.