# The National Grid (Richborough Connection Project) Development Consent Order 2017, Paragraph 7: Prior to the commencement of the works

Extent: E+W

(1) The licence holder must submit a detailed method statement at least 2 months prior to the commencement of the first licensed activity for approval by the MMO.
(2) The authorised development must be undertaken in accordance with the approved method statement.

---