# The National Grid (Yorkshire Green Energy Enablement Project) Development Consent Order 2024, Article 8: Planning Permission

Extent: E+W+S

If planning permission is issued or granted pursuant to the 1990 Act for development any part of which is within the Order limits that is—
(a) not itself a nationally significant infrastructure project under the 2008 Act or part of such a project; and
(b) required to complete or enable the construction, use or operation of any part of the development authorised by this Order,
then the carrying out, use or operation of such development under the terms of the planning permission does not constitute a breach of the terms of this Order.

---
Source: https://www.legislation.gov.uk/uksi/2024/393/article/8 (the official version)
Page: https://openlegislation.uk/national-grid-yorkshire-green-energy-enablement-project-development-consent-order-2024/article-8
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.