# The National Grid (Yorkshire Green Energy Enablement Project) Development Consent Order 2024, Article 9: Application of the 1990 Act

Extent: E+W+S

(1) Where land within the Order limits is used for temporary construction works, section 57(2) (planning permission required for development) of the 1990 Act applies as if the development consent granted by this Order were planning permission granted for a limited period.
(2) Development consent granted by this Order is to be treated as specific planning permission for the purposes of section 264(3)(a) (cases in which land is to be treated as not being operational land for the purposes of that Act) of the 1990 Act.
(3) In the exercise of the power under paragraphs (1) and (2) of article 11 (street works) the undertaker is to be deemed to be the highway authority for the purposes of section 55(2)(b) (meaning of “development” and “new development”) of the 1990 Act.

---
Source: https://www.legislation.gov.uk/uksi/2024/393/article/9 (the official version)
Page: https://openlegislation.uk/national-grid-yorkshire-green-energy-enablement-project-development-consent-order-2024/article-9
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.