  "url": "https://openlegislation.uk/national-grid-yorkshire-green-energy-enablement-project-development-consent-order-2024/schedule-1/crossheading-overhead-electric-lines-and-monk-fryston-substation",
  "json_url": "https://openlegislation.uk/national-grid-yorkshire-green-energy-enablement-project-development-consent-order-2024/schedule-1/crossheading-overhead-electric-lines-and-monk-fryston-substation.json",
  "legislation": "uksi/2024/393",
  "legislation_title": "The National Grid (Yorkshire Green Energy Enablement Project) Development Consent Order 2024",
  "legislation_url": "https://openlegislation.uk/national-grid-yorkshire-green-energy-enablement-project-development-consent-order-2024",
  "path": "schedule/1/crossheading/overhead-electric-lines-and-monk-fryston-substation",
  "kind": "crossheading",
  "number": null,
  "heading": "OVERHEAD ELECTRIC LINES AND MONK FRYSTON SUBSTATION",
  "text": "In North Yorkshire\nWorks to reconfigure the XC overhead electric line through construction and installation of new sections and dismantling of existing sections shown on section E, sheet 7 and section F, sheet 1 of the works plan, comprising—\n(a) the construction and installation of an overhead electric line from XC521 to XC526 and from XC526 to XC527, and from XC526 to XC528, including the construction and installation of five pylons, conductors, fibre optic earthwires, insulators, fittings, and connections into the Monk Fryston Substation referred to at Work No. 11;\n(b) the dismantling and removal of an overhead electric line from XC521 to XC525T, including removal of four pylons, conductors, insulators, fittings, fibre optic earthwires and foundations;\n(c) the construction and installation of a temporary diversion of the existing XC overhead electric line from XC522T to XC525T, including conductors, insulators, fittings and two temporary structures; and\n(d) the installation of one temporary construction compound.",
  "extent": "E+W+S",
  "status": null,
  "version": "current",
  "annotations": [],
  "outstanding_effects": [],
  "provenance": {
    "source": "legislation.gov.uk",
    "source_url": "https://www.legislation.gov.uk/uksi/2024/393/schedule/1/crossheading/overhead-electric-lines-and-monk-fryston-substation",
    "retrieved_at": "2026-10-28T21:32:16.250831+00:00"
  },
  "licence": "Open Government Licence v3.0",
  "licence_url": "https://www.nationalarchives.gov.uk/doc/open-government-licence/version/3/",
  "attribution": "Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives."
}