  "legislation": "uksi/2024/393",
  "legislation_title": "The National Grid (Yorkshire Green Energy Enablement Project) Development Consent Order 2024",
  "legislation_url": "https://openlegislation.uk/national-grid-yorkshire-green-energy-enablement-project-development-consent-order-2024",
  "path": "schedule/13/part/3",
  "kind": "part",
  "number": "3",
  "heading": "NGN",
  "text": "North Yorkshire Council\n(1) Plot number of land shown on land plan\n(2) Purpose for which rights over land may be acquired or restrictive covenants imposed\n(3) Relevant part of the authorised development\nD1-10\nCompulsory Acquisition of Rights for Authorised Development\nWork Nos. 8, U8\nD1-15, D1-19, D1-84\nCompulsory Acquisition of Rights for Authorised Development\nWork Nos. 8, U8",
  "extent": "E+W+S",
  "status": null,
  "version": "current",
  "annotations": [
    {
      "type": "I",
      "label": "I1",
      "text": "Sch. 13 Pt. 3 in force at 5.4.2024, see art. 1"
    }
  ],
  "outstanding_effects": [],
  "provenance": {
    "source": "legislation.gov.uk",
    "source_url": "https://www.legislation.gov.uk/uksi/2024/393/schedule/13/part/3",
    "retrieved_at": "2026-10-28T21:32:16.250831+00:00"
  },
  "licence": "Open Government Licence v3.0",
  "licence_url": "https://www.nationalarchives.gov.uk/doc/open-government-licence/version/3/",
  "attribution": "Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives."
}