# The National Grid (Yorkshire Green Energy Enablement Project) Development Consent Order 2024, Paragraph 20: Access to work – provision of information

Extent: E+W+S

(1) The undertaker on being given reasonable notice must—
(a) at all reasonable times allow reasonable facilities to the engineer for access to a specified work during its construction and, to the extent that it would affect the waterway or any function of the Trust, maintenance; and
(b) supply the engineer with all such information as the engineer may reasonably require with regard to a specified work or the method of constructing and maintaining it.
(2) The Trust on being given reasonable notice must supply the undertaker with such information as it may reasonably require with regard to such works or the method of constructing them and the undertaker must reimburse the Trust’s reasonable costs in relation to the supply of such information.

---
Source: https://www.legislation.gov.uk/uksi/2024/393/schedule/15/paragraph/20 (the official version)
Page: https://openlegislation.uk/national-grid-yorkshire-green-energy-enablement-project-development-consent-order-2024/schedule-15/paragraph-20
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.