# The National Grid (Yorkshire Green Energy Enablement Project) Development Consent Order 2024, Paragraph 42

Extent: E+W+S

In the assessment of any sums payable to Network Rail under this Part there must not be taken into account any increase in the sums claimed that is attributable to any action taken by or any agreement entered into by Network Rail if that action or agreement was not reasonably necessary and was taken or entered into with a view to obtaining the payment of those sums by the undertaker under this Part or increasing the sums so payable.

---
Source: https://www.legislation.gov.uk/uksi/2024/393/schedule/15/paragraph/42 (the official version)