# The National Grid (Yorkshire Green Energy Enablement Project) Development Consent Order 2024, Paragraph 14: Highway works

Extent: E+W+S

(1) No work to construct or temporarily alter any new or existing means of access to a highway to be used by vehicular traffic may commence until written details of the design and layout of that means of access has been submitted to and approved by the relevant highway authority.
(2) The highway accesses must be constructed in accordance with the details approved under paragraph (1) unless otherwise agreed in writing with the relevant highway authority.

---
Source: https://www.legislation.gov.uk/uksi/2024/393/schedule/3/paragraph/14 (the official version)
Page: https://openlegislation.uk/national-grid-yorkshire-green-energy-enablement-project-development-consent-order-2024/schedule-3/paragraph-14
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.