# The National Grid (Yorkshire Green Energy Enablement Project) Development Consent Order 2024, Paragraph 4: Stages of authorised development

Extent: E+W+S

(1) The authorised development may not commence until a written scheme setting out the stages of the authorised development has been submitted to the relevant planning authority, which scheme may subsequently be amended from time to time as notified to the relevant planning authority.
(2) The authorised development must be constructed in accordance with the written scheme setting out the stages of the authorised development submitted under paragraph (1).

---