# The National Grid (Yorkshire Green Energy Enablement Project) Development Consent Order 2024, Paragraph 5: Construction management plans

Extent: E+W+S

(1) All construction works for the authorised development must be carried out in accordance with the construction management plans referred to in paragraph (2), unless otherwise agreed with the relevant planning authority or the highway authority, as may be appropriate to the relevant plan, scheme or strategy concerned.
(2) The construction management plans, which specify the measures to be used to minimise the impacts of construction works, are the following plans, schemes and strategies—
(a) the code of construction practice;
(b) the archaeological written scheme of investigation;
(c) the biodiversity mitigation strategy;
(d) the construction traffic management plan;
(e) the public rights of way management plan; and
(f) the noise and vibration management plan.
(3) For the avoidance of doubt, all pre-commencement works must be carried out in accordance with the construction management plans and the outline soil management plan.

---
Source: https://www.legislation.gov.uk/uksi/2024/393/schedule/3/paragraph/5 (the official version)
Page: https://openlegislation.uk/national-grid-yorkshire-green-energy-enablement-project-development-consent-order-2024/schedule-3/paragraph-5
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.