  "url": "https://openlegislation.uk/national-grid-yorkshire-green-energy-enablement-project-development-consent-order-2024/schedule-5/paragraph-7",
  "json_url": "https://openlegislation.uk/national-grid-yorkshire-green-energy-enablement-project-development-consent-order-2024/schedule-5/paragraph-7.json",
  "legislation": "uksi/2024/393",
  "legislation_title": "The National Grid (Yorkshire Green Energy Enablement Project) Development Consent Order 2024",
  "legislation_url": "https://openlegislation.uk/national-grid-yorkshire-green-energy-enablement-project-development-consent-order-2024",
  "path": "schedule/5/paragraph/7",
  "kind": "paragraph",
  "number": "7",
  "heading": null,
  "text": "On the date specified in any notice under paragraph (6) of this schedule—\n(a) NGN is to cease to have the benefit of sub-paragraph (1) of article 3 (development consent etc. granted by the Order) and sub-paragraph (1) of article 6 (benefit of the Order);\n(b) NGN is to cease to be an undertaker for the installation of the NGN Works but remains an undertaker for the purposes of keeping installed the underground gas pipelines included in the NGN Works; and\n(c) references to NGN in article 39 (temporary use of land for maintaining the authorised development) are to be read as including National Grid.",
  "extent": "E+W+S",
  "status": null,
  "version": "current",
  "annotations": [
    {
      "type": "I",
      "label": "I1",
      "text": "Sch. 5 para. 7 in force at 5.4.2024, see art. 1"
    }
  ],
  "outstanding_effects": [],
  "provenance": {
    "source": "legislation.gov.uk",
    "source_url": "https://www.legislation.gov.uk/uksi/2024/393/schedule/5/paragraph/7",
    "retrieved_at": "2026-10-28T21:32:16.250831+00:00"
  },
  "licence": "Open Government Licence v3.0",
  "licence_url": "https://www.nationalarchives.gov.uk/doc/open-government-licence/version/3/",
  "attribution": "Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives."
}