# The National Grid (Yorkshire Green Energy Enablement Project) Development Consent Order 2024, North Yorkshire Council

Extent: E+W+S

(1) Street subject to alteration of layout
(2) Description of alteration of layout as shown on the access, rights of way and public rights of navigation plan
Overton Road
Provision of carriageway widening to aid heavy goods vehicle manoeuvres and access/egress to the proposed Overton Substation. Works comprising site clearance, construction of new road surface, white lining, kerbing and a suitable drainage system as required as shown as JW02 Section B, Sheet 2.
U1720 (ORPA)
At bellmouth AP98 as shown on Section B, Sheet 1 the creation of an access point of sufficient size to accommodate access and egress of vehicles for operation and maintenance requirements of the site. Works comprising site clearance, construction of new road surface, white lining, kerbing and a suitable drainage system as required.
A659
At bellmouth AP31 as shown on Section D Sheet 1 the creation of an access point of sufficient size to accommodate access and egress of vehicles for operation and maintenance requirements. Works comprising site clearance, construction of new road surface, white lining, kerbing and a suitable drainage system as required.
Garnet Lane
At bellmouth AP34 as shown on Section D Sheet 1 the creation of an access point of sufficient size to accommodate access and egress of vehicles for operation and maintenance requirements. Works comprising site clearance, construction of new road surface, white lining, kerbing and a suitable drainage system as required.
Rawfield Lane
At bellmouth AP3 as shown on Section F Sheet 1 the creation of an access point of sufficient size to accommodate access and egress of vehicles for operation and maintenance requirements. Works comprising site clearance, construction of new road surface, white lining, kerbing and a suitable drainage system as required.
Overton Road
At bellmouth AP89 as shown on Section B Sheet 2 the creation of an access point of sufficient size to accommodate access and egress of vehicles for operation and maintenance requirements. Works comprising site clearance, construction of new road surface, white lining, kerbing and a suitable drainage system as required.

---
Source: https://www.legislation.gov.uk/uksi/2024/393/schedule/7/part/1/crossheading/north-yorkshire-council (the official version)
Page: https://openlegislation.uk/national-grid-yorkshire-green-energy-enablement-project-development-consent-order-2024/schedule-7/part-1/crossheading-north-yorkshire-council
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.