In Schedule 2, for paragraph 43 (sub-contracting of clinical matters) substitute—

“Sub-contracting of clinical matters

43
(1)

The contractor must not sub-contract any of its rights or duties under the agreement in relation to clinical matters to any person unless—

(a)

in all cases, including those duties relating to out of hours services to which paragraph 43A (sub-contracting out of hours services) applies, the contractor has taken reasonable steps to satisfy itself that—

(i)

it is reasonable in all the circumstances to do so, and

(ii)

the person to whom any of those rights or duties is sub-contracted is qualified and competent to provide the service, and

(b)

except in cases to which paragraph 43A applies, the contractor has given notice in writing to NHS England of its intention to sub-contract, as soon as reasonably practicable before the date on which the proposed sub-contract is intended to come into effect.

(2)

Sub-paragraph (1)(b) does not apply to a contract for services with a health care professional for the provision by that professional personally of clinical services.

(3)

A notice given under sub-paragraph (1)(b) must include—

(a)

the name and address of the proposed sub-contractor,

(b)

the duration of the proposed sub-contract,

(c)

the services to be covered by the proposed sub-contract, and

(d)

the address of any premises to be used as practice premises under the proposed sub-contract.

(4)

On receipt of a notice given under sub-paragraph (1)(b), NHS England may request such further information relating to the proposed sub-contract as appears to it to be reasonable, and the contractor must supply such information to NHS England promptly.

(5)

The contractor must not proceed with a contract or, if the contract has already taken effect, the contractor must take steps to terminate it, where—

(a)

before the end of the period of 28 days beginning with the date on which NHS England received a notice from the contractor under sub-paragraph (1)(b), NHS England gives notice in writing of its objection to the contract on the grounds that the contract would—

(i)

put the safety of the contractor's patients at serious risk, or

(ii)

put NHS England at risk of material financial loss, or

(b)

the sub-contractor would be unable to meet the contractor's obligations under the agreement.

(6)

A notice given by NHS England under sub-paragraph (5)(a) must include a statement of the reasons for NHS England's objection.

(7)

Sub-paragraphs (1) to (6) also apply in relation to any renewal, or material variation, of a contract in relation to clinical matters.

(8)

Where NHS England does not give notice of an objection under sub-paragraph (5), the parties to the agreement are deemed to have agreed a variation of the agreement which has the effect of adding the address of any premises which was notified to NHS England under sub-paragraph (3)(d) to the list of practice premises and, in these circumstances, paragraph 52(1) (variation of an agreement) does not apply.

(9)

Subject to sub-paragraph (10), a sub-contract entered into by a contractor must prohibit the sub-contractor from sub-contracting any of the clinical services that it has agreed with the contractor to provide under the sub-contract.

(10)

A sub-contract entered into by the contractor may allow the sub-contractor to sub-contract clinical services the contractor has agreed to provide under the Network Contract Directed Enhanced Service Scheme, pursuant to the Primary Medical Services (Directed Enhanced Services) Directionsf1, provided the contractor obtains the written approval of NHS England prior to the sub-contractor sub-contracting those services.

(11)

The contractor must not sub-contract any of its rights or duties under the agreement in relation to the provision of essential services to a company or firm that is—

(a)

wholly or partly owned by the contractor, or by any former or current employee of, or partner or shareholder in, the contractor,

(b)

formed by or on behalf of the contractor, or from which the contractor derives or may derive a pecuniary benefit, or

(c)

formed by or on behalf of a former or current employee of, or partner or shareholder in, the contractor, or from which such a person derives or may derive a pecuniary benefit,

where sub-paragraph (12) applies to that company or firm.

(12)

This sub-paragraph applies to a company or firm which is or was formed wholly or partly for the purpose of avoiding the restrictions on the sale of goodwill of a medical practice in section 259 of the Actf2 (sale of medical practices), and Schedule 21 to the Act (prohibition of sale of medical practices), or any regulations made wholly or partly under those provisions of the Act.

Sub-contracting out of hours services

43A
(1)

A contractor must not sub-contract all or part of its duty to provide out of hours services under the agreement to a person other than those specified in sub-paragraph (2) without the prior written approval of NHS England.

(2)

The persons specified in this sub-paragraph are—

(a)

a person who holds a contract made in accordance with the General Medical Services Contracts Regulations and under such contract is required to provide the equivalent of essential services to its patients during all or part of the out of hours period,

(b)

a provider of an agreement which includes the provision of out of hours services,

(c)

a health care professional, not falling within paragraph (a) or (b), who is to provide the out of hours services personally under a contract for services, or

(d)

a group of medical practitioners, whether in partnership or not, who provide out of hours services for each other under informal rota agreements.

(3)

The requirement in sub-paragraph (1) to obtain prior written approval does not apply in any case where a contractor sub-contracts all or part of its duty to provide out of hours services under the agreement on a short term or occasional basis.

(4)

An application for approval under sub-paragraph (1) must be made by the contractor in writing to NHS England and must state—

(a)

the name and address of the proposed sub-contractor,

(b)

the duration of the proposed sub-contract,

(c)

the services to be covered by the sub-contract,

(d)

the address of any premises to be used as practice premises under the sub-contract, and

(e)

the manner in which the sub-contractor proposes to meet the contractor's obligations under the agreement in respect of the services to be covered by the sub-contract.

(5)

Before the end of the period of seven days beginning with the date on which NHS England received the application under sub-paragraph (4), NHS England may request such further information relating to arrangements under the proposed sub-contract as appears to it to be reasonable.

(6)

Where NHS England receives an application which meets the requirements specified in sub-paragraph (4), or receives any further information requested under sub-paragraph (5) in relation to an application, NHS England must, before the end of the period of 28 days beginning with the date on which it received the application or that information (whichever is the latest)—

(a)

approve the application;

(b)

approve the application subject to conditions; or

(c)

refuse the application.

(7)

NHS England must not refuse the application if it is satisfied that the arrangements covered by the proposed sub-contract would, in respect of the services to be provided, enable the contractor to satisfactorily meet its obligations under the agreement and would not—

(a)

put the safety of the contractor's patients at serious risk, or

(b)

put NHS England at risk of material financial loss.

(8)

NHS England must give notice in writing to the contractor of its decision on the application and, where it refuses an application, it must include in the notice a statement of the reasons for its refusal.

(9)

Where NHS England approves an application under this paragraph, the parties to the agreement are deemed to have agreed a variation of the agreement which has the effect of adding to the list of practice premises, for the purposes of the provision of services in accordance with that application, any premises the address of which was notified to NHS England under sub-paragraph (4)(d) and, in these circumstances, paragraph 52(1) (variation of an agreement) does not apply.

(10)

Sub-paragraphs (1) to (9) also apply in relation to any renewal or material variation of a sub-contract in relation to out of hours services.

(11)

A sub-contract entered into by a contractor must prohibit the sub-contractor from sub-contracting the out of hours services that it has agreed with the contractor to provide under the sub-contract.”.

Annotations

Footnotes

f1

These directions are available online at: https://www.gov.uk/government/publications/primary-medical-services-directed-enhanced-services-directions. Hard copies are available from the Department of Health and Social Care, 39 Victoria Street, London, SW1H 0EU.

f2

Section 259 was amended by paragraph 132 of Schedule 4 to the Health and Social Care Act 2012 (c. 7) and paragraph 1 of Schedule 1 to the Health and Care Act 2022 (c. 31).