# The Net Zero Teesside (Amendment) Order 2025, Article 14: Amendment to Schedule 1 (authorised development)


In Schedule 1 (authorised development), before Work No. 7 insert—
“Work No. 6A – above ground installations required to facilitate Work No. 6, comprising—
(a) above and below ground piping;
(b) a PIG launcher;
(c) remotely operated valves and valve bypass; and
(d) instrumentation and electrical kiosk.”

---