Article 3 Amendment to Schedule 15 (design parameters) of the 2024 Order
In Schedule 15 (design parameters), Table 14 is amended as follows—
(a)
In the row labelled “Heat recovery steam generator stack”, before “(inner diameter)”, for “6.5 m” substitute “9.0 m”; and
(b)
In the row labelled “Absorber stack”, before “(inner diameter)”, for “6.6 m” substitute “7.0 m”.