# The Net Zero Teesside Order 2024, Paragraph 13: Pre-construction

Extent: E+W+S

(1) A marine method statement must be submitted to the MMO at least three months prior to the proposed commencement of the licensed activities or part of the licenced activities.
(2) A marine method statement submitted pursuant to sub-paragraph (1) for licensed activities must include details of—
(a) methods of dredging to be employed and associated disposal arrangements;
(b) the micro-bored tunnel installation and methodology;
(c) the discharge head installation technique and methodology;
(d) rock armour specification, provenance and installation technique; and
(e) an indicative programme for the delivery of the licensed activities.
(3) A marine method statement submitted pursuant to sub-paragraph (1) must—
(a) only include details of the licensed activities in so far as they are required; and
(b) be scaled to correspond to the final requirements of the authorised development.
(4) No part of the licensed activities may commence until the marine method statement for that part has been approved in writing by the MMO.
(5) A marine method statement approved pursuant to sub-paragraph (4) may be amended from time to time subject to approval in writing from the MMO.
(6) The licensed activities must be carried out in accordance with the marine method statement approved pursuant to sub-paragraphs (5) and (6).

---
Source: https://www.legislation.gov.uk/uksi/2024/174/schedule/10/paragraph/13 (the official version)