  "url": "https://openlegislation.uk/net-zero-teesside-order-2024/schedule-12/paragraph-125/enacted",
  "json_url": "https://openlegislation.uk/net-zero-teesside-order-2024/schedule-12/paragraph-125/enacted.json",
  "legislation": "uksi/2024/174",
  "legislation_title": "The Net Zero Teesside Order 2024",
  "legislation_url": "https://openlegislation.uk/net-zero-teesside-order-2024/enacted",
  "path": "schedule/12/paragraph/125",
  "kind": "paragraph",
  "number": "125",
  "heading": null,
  "text": "(1) The undertaker must pay to Network Rail all reasonable costs, charges, damages and expenses not otherwise provided for in this Part of this Schedule which may be occasioned to or reasonably incurred by Network Rail—\n(a) by reason of the construction, maintenance or operation of a specified work or the failure thereof it;\n(b) by reason of any act or omission of the undertaker or of any person in its employ or of its contractors or others within the control of the undertaker whilst engaged upon a specified work;\n(c) by reason of any act or omission of the undertaker or of any person in its employ or of its contractors or others within the control of the undertaker whilst accessing to or egressing from the authorised development;\n(d) in respect of any damage caused to or additional maintenance required to railway property or any such interference or obstruction or delay to the operation of the railway as a result of access to or egress from the authorised development by the undertaker or any person in its employ or of its contractors or others within the control of the undertaker; or\n(e) in respect of costs incurred by Network Rail in complying with any railway operational procedure or obtaining any regulatory consents which procedures are required to be followed or consents obtained to facilitate the carrying out or operation of the authorised development,\nand the undertaker must indemnify and keep indemnified Network Rail from and against all claims and demands arising out of or in connection with a specified work or any such failure, act or omission and the fact that any act or thing may have been done by Network Rail on behalf of the undertaker or in accordance with plans approved by the engineer or in accordance with any requirement of the engineer or under the engineer’s supervision shall not (if it was done without negligence on the part of Network Rail or any person in its employ or of its contractors or agents) excuse the undertaker from any liability under the provisions of this sub-paragraph.\n(2) Network Rail must—\n(a) give the undertaker reasonable written notice of any such claims or demands;\n(b) not make any settlement or compromise of such a claim or demand without the prior consent of the undertaker; and\n(c) take all steps as are within its control and are reasonable in the circumstances to mitigate any liabilities relating to such claims or demands and to minimise any costs, expenses, loss, demands and penalties to which the indemnity under this paragraph 124 applies. If requested to do so by the undertaker, Network Rail is to provide an explanation of how the claim has been minimised or details to substantiate any cost or compensation claimed pursuant to sub-paragraph (1). The undertaker is to only be liable under this paragraph 124 for claims reasonably incurred by Network Rail.\n(3) In no circumstances is the undertaker liable to Network Rail under sub-paragraph (1) for any indirect or consequential loss or loss of profits, save that the sums payable by the undertaker under sub-paragraph (1) shall if relevant include a sum equivalent to the relevant costs.\n(4) Subject to the terms of any agreement between Network Rail and a train operator regarding the timing or method of payment of the relevant costs in respect of that train operator, Network Rail must promptly pay to each train operator the amount of any sums which Network Rail receives under sub-paragraph (3) which relates to the relevant costs of that train operator.\n(5) The obligation under sub-paragraph (3) to pay Network Rail the relevant costs shall, in the event of default, be enforceable directly by any train operator concerned to the extent that such sums would be payable to that operator pursuant to sub-paragraph (4).\n(6) In this paragraph—\n“the relevant costs” means the costs, direct losses and expenses (including loss of revenue) reasonably incurred by each train operator as a consequence of any specified work including but not limited to any restriction of the use of Network Rail’s railway network as a result of the construction, maintenance or failure of a specified work or any such act or omission as mentioned in sub-paragraph (1); and\n“train operator” means any person who is authorised to act as the operator of a train by a licence under section 8 of the Railways Act 1993.",
  "extent": "E+W+S",
  "status": null,
  "version": "enacted",
  "annotations": [
    {
      "type": "F",
      "label": "F1",
      "text": "Sch. 12 para. 125(1)(e) comma inserted (21.12.2024) by The Net Zero Teesside (Correction) Order 2024 (S.I. 2024/1384), art. 1, Sch. Table"
    },
    {
      "type": "I",
      "label": "I1",
      "text": "Sch. 12 para. 125 in force at 11.3.2024, see art. 1"
    }
  ],
  "outstanding_effects": [],
  "provenance": {
    "source": "legislation.gov.uk",
    "source_url": "https://www.legislation.gov.uk/uksi/2024/174/schedule/12/paragraph/125",
    "retrieved_at": "2026-10-28T21:34:40.750770+00:00"
  },
  "licence": "Open Government Licence v3.0",
  "licence_url": "https://www.nationalarchives.gov.uk/doc/open-government-licence/version/3/",
  "attribution": "Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives."
}