# The Net Zero Teesside Order 2024, Paragraph 146

Extent: E+W+S

If Northern Powergrid at any time becomes aware that an estimate agreed is likely to be exceeded, it must forthwith notify the undertaker and must submit a revised estimate of the relevant costs and expenses to the undertaker for agreement.

---
Source: https://www.legislation.gov.uk/uksi/2024/174/schedule/12/paragraph/146 (the official version)