# The Net Zero Teesside Order 2024, Paragraph 149

Extent: E+W+S

Any difference under the provisions of this Part of this Schedule, unless otherwise provided for, is to be referred to and settled by a single arbitrator to be agreed between the parties or, failing agreement, to be appointed on the application of either party (after giving notice in writing to the other) by an independent electrical engineer by or on behalf of the President for the time being of the Institute of Engineering and Technology.

---
Source: https://www.legislation.gov.uk/uksi/2024/174/schedule/12/paragraph/149 (the official version)