# The Net Zero Teesside Order 2024, Paragraph 167: Consent under this Part

Extent: E+W+S

Any approval of PD Teesport required under paragraph 165 must not be unreasonably withheld or delayed but may be given subject to such reasonable requirements as PD Teesport may require to be made for—
(a) the continuing safety, operational activity or business interests of the PD Teesport operations; and
(b) the requirement for PD Teesport to have uninterrupted and unimpeded access (including river access) to PD Teesport operations at all times.

---
Source: https://www.legislation.gov.uk/uksi/2024/174/schedule/12/paragraph/167 (the official version)
Page: https://openlegislation.uk/net-zero-teesside-order-2024/schedule-12/paragraph-167
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.