# The Net Zero Teesside Order 2024, Paragraph 178: Consent under this Part

Extent: E+W+S

Before commencing—
(a) any part of the authorised development which would have an effect on the RBT operations or access to them; or
(b) any activities on or to the RBT site,
the undertaker must submit to RBT the works details for the proposed works or activities and such further particulars as RBT may, not less than 28 days from the day on which the works details are submitted under this paragraph, reasonably require.

---
Source: https://www.legislation.gov.uk/uksi/2024/174/schedule/12/paragraph/178 (the official version)
Page: https://openlegislation.uk/net-zero-teesside-order-2024/schedule-12/paragraph-178
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.