  "heading": "Indemnity",
  "text": "(1) Subject to sub-paragraphs (2) and (3) below, if by reason or in consequence of the construction of any of the works referred to in paragraph 177 or by the use of the RBT site by the undertaker any damage is caused to the RBT site (including the wharf, roadways, any RBT buildings, plant or machinery on the RBT site) or to the RBT operations, or there is any interruption in any service provided, or in the provision by RBT or denial of any services, or in any loss of service from apparatus that is affected by the authorised development the undertaker must—\n(a) bear and pay the cost reasonably incurred by RBT in making good such damage or restoring the provision by RBT of any services; and\n(b) make compensation to RBT for any other expenses, loss, damages, penalty or costs reasonably incurred by RBT (including, without limitation, all costs for the repair or replacement necessitated by physical damage), by reason or in consequence of any such damage or interruption or denial of any service provided by RBT.\n(2) Nothing in sub-paragraph (1) imposes any liability on the undertaker with respect to any damage or interruption to the extent that it is attributable to the act, neglect or default of RBT, its officers, employees, servants, contractors or agents.\n(3) RBT must give the undertaker reasonable notice of any claim or demand that has been made against it in respect of the matters in sub-paragraphs (1)(a) and (b) and no settlement or compromise of such a claim is to be made without the consent of the undertaker such consent not to be unreasonably withheld.\n(4) RBT must use its reasonable endeavours to mitigate in whole or in part and to minimise any costs, expenses, loss, demands, and penalties to which the indemnity under this paragraph 184 applies. If requested to do so by the undertaker, RBT must provide a reasonable explanation of how the claim has been minimised or details to substantiate any cost or compensation claimed pursuant to sub-paragraph (1). The undertaker shall only be liable under this paragraph 184 for claims reasonably incurred by RBT.",
  "extent": "E+W+S",
  "status": null,
  "version": "current",
  "annotations": [
    {
      "type": "F",
      "label": "F1",
      "text": "Word in Sch. 12 para. 185(3) substituted (21.12.2024) by The Net Zero Teesside (Correction) Order 2024 (S.I. 2024/1384), art. 1, Sch. Table"
    },
    {
      "type": "I",
      "label": "I1",
      "text": "Sch. 12 para. 185 in force at 11.3.2024, see art. 1"
    }
  ],
  "outstanding_effects": [],
  "provenance": {
    "source": "legislation.gov.uk",
    "source_url": "https://www.legislation.gov.uk/uksi/2024/174/schedule/12/paragraph/185",
    "retrieved_at": "2026-10-28T21:34:40.750770+00:00"
  },
  "licence": "Open Government Licence v3.0",
  "licence_url": "https://www.nationalarchives.gov.uk/doc/open-government-licence/version/3/",
  "attribution": "Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives."
}