# The Net Zero Teesside Order 2024, Paragraph 194: Notice of works

Extent: E+W+S

The undertaker must provide to SABIC a minimum of 28 days’ notice prior to commencing any relevant work in order that an engineer can be made available to observe the relevant works and, when required, advise on the necessary safety precautions.

---
Source: https://www.legislation.gov.uk/uksi/2024/174/schedule/12/paragraph/194 (the official version)
Page: https://openlegislation.uk/net-zero-teesside-order-2024/schedule-12/paragraph-194
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.