# The Net Zero Teesside Order 2024, Paragraph 197: Further provisions about works

Extent: E+W+S

(1) Where excavation of trenches (including excavation by dredging) adjacent to a pipeline affects its support, the pipeline must be supported in a manner approved by SABIC.
(2) Where the undertaker proposes to carry out excavations which might affect above ground structures such as pipeline supports in the pipeline corridor, the undertaker must calculate the zone of influence of those excavations and provide those calculations to SABIC under paragraph 189.

---
Source: https://www.legislation.gov.uk/uksi/2024/174/schedule/12/paragraph/197 (the official version)
Page: https://openlegislation.uk/net-zero-teesside-order-2024/schedule-12/paragraph-197
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.