# The Net Zero Teesside Order 2024, Paragraph 199: Further provisions about works

Extent: E+W+S

(1) A minimum clearance of 1500 millimetres must be maintained between any part of the authorised development and any affected asset (whether that part of the authorised development is parallel to or crosses the pipeline) unless otherwise agreed with SABIC.
(2) No manholes or chambers are to be built over or round the pipelines.

---
Source: https://www.legislation.gov.uk/uksi/2024/174/schedule/12/paragraph/199 (the official version)
Page: https://openlegislation.uk/net-zero-teesside-order-2024/schedule-12/paragraph-199
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.