# The Net Zero Teesside Order 2024, Paragraph 203: Access for construction and maintenance

Extent: E+W+S

(1) Before carrying out any construction or maintenance works affecting SABIC’s access rights over the access roads, the undertaker must prepare a draft construction access plan and consult on the draft construction access plan with SABIC.
(2) The undertaker must take account of the responses to any consultation referred to in sub-paragraph (1) before approving the construction access plan.

---
Source: https://www.legislation.gov.uk/uksi/2024/174/schedule/12/paragraph/203 (the official version)
Page: https://openlegislation.uk/net-zero-teesside-order-2024/schedule-12/paragraph-203
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.