# The Net Zero Teesside Order 2024, Paragraph 205: Access for construction and maintenance

Extent: E+W+S

(1) No works affecting access rights over the access roads are to commence until 30 days after a copy of the approved construction access plan is served on SABIC.
(2) Where SABIC or the undertaker refers the construction access plan to arbitration for determination under paragraph 211, no works affecting access rights over the access roads may commence until that determination has been provided.
(3) In carrying out construction or maintenance works the undertaker must at all times comply with the construction access plan.

---
Source: https://www.legislation.gov.uk/uksi/2024/174/schedule/12/paragraph/205 (the official version)