# The Net Zero Teesside Order 2024, Paragraph 219: Consent under this Part in connection with Sembcorp operations

Extent: E+W+S

The works referred to in paragraph 217 must not be commenced until the works details in respect of those works submitted under that paragraph have been approved by Sembcorp.

---